Understand 
  These Three Estimating Concepts
             
   
      
          
        
             
   
      
          
  
  
Estimate in Phases
One of the most difficult aspects of 
  planning 
  projects is the estimating process. It can be hard to know exactly what work will be 
  needed in the distant future. It can be difficult to define and estimate 
  work that will be done three months from now. It's harder to estimate 
  six months in the future. Nine months is even harder. There is 
  more and more estimating uncertainty associated with work that is 
  farther and farther out in the future.
A good 
  approach for larger projects is to 
  break the work into a series of smaller projects, each of which can be 
  planned, estimated and managed separately with a much higher likelihood 
  of success. From an estimating perspective, the closest 
  project can be estimated more precisely, with the subsequent projects 
  estimated with a higher level of uncertainty. When one project 
  completes, the next project can be estimated with a higher degree of 
  confidence, with estimates refined for the remaining projects. This 
  technique also provides checkpoints at the end of each project so that 
  the entire initiative can be revalidated based on current estimates to 
  ensure that it is still viable and worth continuing.
Estimate Fixed Costs and Variable 
  Costs
You may hear the terms fixed and variable 
  cost when you are estimating the cost of a project. Variable costs are 
  those that change relative to how many units are being used. An obvious 
  variable cost on a project is contract labor. The more hours you use 
  from a contactor, the more the cost to the project. The 
  cost of contract labor is variable depending on the number of hours 
  worked. 
Fixed costs are those that are basically 
  the same for the project regardless of the resources being used. For 
  instance, if you were building a house, the cost of 
  the lot would be fixed and would not change based on 
  the size of the house you built. Similarly, if you outsource part of a project to a 
  third party for a fixed price, it becomes a fixed cost to the project as 
  well. Even if the work takes longer or shorter than estimated, your 
  project cost should still be the agreed upon fixed cost. 
Estimate Time-Constrained and 
  Resource-Constrained Activities
Activities can be classified as time or 
  resource-constrained based on whether the duration can change if more 
  resources are applied. An activity is resource-constrained if the 
  duration changes based on the number of resources applied. For instance, 
  you might estimate that it will take 80 hours for one person to build a 
  roof on top of a house. If the person worked forty hours per week, it 
  would take two weeks to complete the job. If you applied two people to 
  the job, the effort is still be 200 total effort hours, but the job 
  would only take one week to complete. 
On the other hand, if an activity is 
  time-constrained, the duration remains the same regardless of the number 
  of resources applied. For example, lets say one person attends a three-day class. If you send two people to the 
  class, the class does not get shorter; it still takes three days. 
  Likewise, the time it takes for concrete to dry, or to mail a letter, is 
  not impacted by the number of people involved. They just take a certain 
  amount of time. If you find that applying resources has no impact on the 
  project duration (or very little impact), then the activity is 
  time-constrained.